船体 QC 实用对话(中英对照)

A: 外板的曲面展开采用测地线法,精度能满足要求吗?B: 能满足,偏差可控制在≤2mm/m。A: The geodesic line method is used for the curved surface development of the shell plate. Can the a...
  1. A: 外板的曲面展开采用测地线法,精度能满足要求吗?
    B: 能满足,偏差可控制在≤2mm/m。
    A: The geodesic line method is used for the curved surface development of the shell plate. Can the accuracy meet the requirements?
    B: Yes, the deviation can be controlled within ≤2mm/m.

  2. A: 抛丸后的钢材表面有局部未清理到的锈蚀,是覆盖率不够吗?
    B: 是的,已增加抛丸时间,确保覆盖率达到 100%。
    A: There's local unremoved rust on the shot-blasted steel surface. Is it due to insufficient coverage?
    B: Yes, we've increased the shot blasting time to ensure 100% coverage.

  3. A: 分段焊接后的收缩量超过 5mm/m,需要预放收缩量吗?
    B: 需要,按 0.5% 的比例预放收缩量,抵消焊接变形。
    A: The shrinkage of the section after welding exceeds 5mm/m. Is it necessary to pre-set shrinkage allowance?
    B: Yes, pre-set shrinkage allowance at a ratio of 0.5% to offset welding deformation.

  4. A: 磁粉探伤的磁化电流太小,缺陷显示不清晰。
    B: 增大磁化电流至规定值的 120%,重新检测。
    A: The magnetizing current for magnetic particle inspection is too small, and defect display is unclear.
    B: Increase the magnetizing current to 120% of the specified value and re-test.

  5. A: 板材剪切后的毛刺清除不彻底,会影响装配贴合度。
    B: 增加打磨工序,确保毛刺高度≤0.2mm。
    A: The burrs after plate shearing are not completely removed, which will affect assembly fit.
    B: Add a grinding process to ensure burr height ≤0.2mm.

  6. A: 总段对接时的平面度偏差有 6mm,要求≤4mm。
    B: 用液压千斤顶顶起调整,垫入垫片控制平面度。
    A: The flatness deviation during block butt joint is 6mm, requiring ≤4mm.
    B: Lift and adjust with hydraulic jacks, and insert gaskets to control flatness.

  7. A: 焊接工艺评定中的冲击功值低于标准,需要重新评定吗?
    B: 需要,冲击功需≥34J,重新调整参数进行评定。
    A: The impact energy value in the welding procedure qualification is lower than the standard. Is re-qualification needed?
    B: Yes, the impact energy must be ≥34J. Re-adjust parameters for qualification.

  8. A: 数学放样的型线与实尺样板比对有偏差,原因是什么?
    B: 是样板制作时的回弹导致,已修正放样数据。
    A: There's a deviation between the mathematical lofting line and the full-scale template. What's the reason?
    B: It's caused by springback during template production. The lofting data has been corrected.

  9. A: 酸洗后的钢材放置时间过长,表面产生浮锈。
    B: 缩短放置时间,24 小时内完成底漆喷涂。
    A: The pickled steel has been placed for too long, and surface rust has formed.
    B: Shorten the placement time and complete primer spraying within 24 hours.

  10. A: 肋骨安装的间距累积偏差达到 15mm,超过 10mm 的允许值。
    B: 从基准肋骨开始重新调整,控制单档偏差≤5mm。
    A: The accumulated deviation of frame installation spacing reaches 15mm, exceeding the allowable 10mm.
    B: Readjust from the reference frame to control single-span deviation ≤5mm.

  11. A: 激光切割的焦点偏移导致切口倾斜,角度超过 3°。
    B: 校准焦点位置,确保切口垂直度偏差≤1°。
    A: The laser cutting focus offset causes the cut to tilt, with an angle exceeding 3°.
    B: Calibrate the focus position to ensure cut perpendicularity deviation ≤1°.

  12. A: 密性试验用的压力表精度等级不够,测量误差大。
    B: 更换 1.6 级精度的压力表,确保测量准确。
    A: The accuracy class of the pressure gauge used for tightness test is insufficient, resulting in large measurement error.
    B: Replace with a pressure gauge of class 1.6 to ensure accurate measurement.

  13. A: 分段的临时支撑拆除后产生变形,是支撑数量不足吗?
    B: 是的,已增加 2 个支撑点,待焊接应力释放后再拆除。
    A: The section deforms after removing temporary supports. Is it due to insufficient supports?
    B: Yes, 2 more support points have been added. Remove them after welding stress is released.

  14. A: 焊缝的余高过渡太陡,应力集中明显。
    B: 打磨余高过渡区,使坡度≤1:4。
    A: The weld reinforcement transition is too steep, with obvious stress concentration.
    B: Grind the reinforcement transition area to make the slope ≤1:4.

  15. A: 抛丸用的磨料粒度太大,导致钢材表面粗糙度超标。
    B: 更换粒度为 0.8-1.2mm 的磨料,降低表面粗糙度。
    A: The abrasive particle size for shot blasting is too large, resulting in excessive surface roughness of steel.
    B: Replace with abrasive with particle size 0.8-1.2mm to reduce surface roughness.

  16. A: 板材拼接的焊缝位置与图纸不符,偏移了 100mm。
    B: 按图纸重新调整板缝位置,确保偏差≤50mm。
    A: The position of the plate butt weld does not match the drawing, with an offset of 100mm.
    B: Readjust the plate seam position according to the drawing to ensure deviation ≤50mm.

  17. A: 渗透探伤的渗透剂停留时间不足,细小缺陷未显示。
    B: 延长停留时间至 10 分钟,确保缺陷充分渗透。
    A: The penetrant dwell time for penetrant testing is insufficient, and small defects are not displayed.
    B: Extend the dwell time to 10 minutes to ensure full penetration of defects.

  18. A: 肋骨冷弯后的扭曲度超过 2mm/m,需要矫正吗?
    B: 需要,用专用夹具矫正,确保扭曲度≤1mm/m。
    A: The torsion degree of the cold-bent frame exceeds 2mm/m. Is straightening needed?
    B: Yes, straighten with special clamps to ensure torsion degree ≤1mm/m.

  19. A: 总段的重心位置计算错误,导致吊装时倾斜。
    B: 重新计算重心,调整吊点位置确保平衡。
    A: The calculation of the block's center of gravity is wrong, causing tilt during hoisting.
    B: Recalculate the center of gravity and adjust lifting points to ensure balance.

  20. A: 焊接后的角变形采用水火矫正,温度控制在多少合适?
    B: 控制在 600-800℃,避免超过 Ac3 温度。
    A: What's the appropriate temperature for flame straightening of angular deformation after welding?
    B: Control it at 600-800℃, avoiding exceeding Ac3 temperature.

  21. A: 数学放样的曲线拐点数量超过标准,光顺性不合格。
    B: 采用样条函数重新光顺,减少拐点至零。
    A: The number of curve inflection points in mathematical lofting exceeds the standard, and fairness is unqualified.
    B: Re-fair with spline functions to reduce inflection points to zero.

  22. A: 钢材预处理线的输送速度过快,影响除锈和喷漆质量。
    B: 降低输送速度 20%,确保处理时间充足。
    A: The conveying speed of the steel pretreatment line is too fast, affecting derusting and painting quality.
    B: Reduce the conveying speed by 20% to ensure sufficient processing time.

  23. A: 分段的对接边缘存在波浪变形,间隙忽大忽小。
    B: 用火焰加热矫正波浪变形,使间隙均匀。
    A: The butt edge of the section has wave deformation, with uneven gaps.
    B: Correct wave deformation with flame heating to make the gap uniform.

  24. A: 射线检测的底片黑度不足,影响缺陷识别。
    B: 增加曝光时间,确保黑度达到 2.0-4.0。
    A: The film density of radiographic testing is insufficient, affecting defect identification.
    B: Increase exposure time to ensure density reaches 2.0-4.0.

  25. A: 板材的厚度方向存在偏差,一边厚一边薄。
    B: 与钢厂沟通,要求厚度公差控制在 ±0.3mm 内。
    A: There's a deviation in the thickness direction of the plate, with one side thicker than the other.
    B: Communicate with the steel mill to require thickness tolerance within ±0.3mm.

  26. A: 肋骨与外板的焊接采用间断焊,焊段长度符合要求吗?
    B: 符合,焊段长 50mm,间距 100mm,满足工艺规定。
    A: Intermittent welding is used for the frame and shell plate. Does the weld segment length meet the requirements?
    B: Yes, the segment length is 50mm and spacing is 100mm, meeting process regulations.

  27. A: 套料时未考虑切割余量,导致零件尺寸偏小。
    B: 增加 3mm 的切割余量,重新套料排版。
    A: Cutting allowance was not considered during nesting, resulting in small part dimensions.
    B: Add 3mm cutting allowance and re-nest.

  28. A: 等离子切割的喷嘴磨损,导致切口宽度增大。
    B: 更换新喷嘴,控制切口宽度≤3mm。
    A: The plasma cutting nozzle is worn, resulting in increased kerf width.
    B: Replace with a new nozzle to control kerf width ≤3mm.

  29. A: 总段合拢后的中心线偏差达到 8mm,需要调整吗?
    B: 需要,用绞车牵引调整,确保偏差≤5mm。
    A: The centerline deviation after block joining reaches 8mm. Is adjustment needed?
    B: Yes, adjust with winch traction to ensure deviation ≤5mm.

  30. A: 焊接用的焊丝直径选错了,应该用 φ1.2mm 却用了 φ1.6mm。
    B: 立即更换焊丝,按正确直径施焊。
    A: The wrong diameter of welding wire was used; φ1.2mm should be used instead of φ1.6mm.
    B: Replace the wire immediately and weld with the correct diameter.

  31. A: 外板的曲面展开采用切面展开法,与测地线法相比精度如何?
    B: 稍低,但偏差仍可控制在≤3mm/m,满足要求。
    A: The tangent development method is used for the shell plate's curved surface. How does its accuracy compare with the geodesic method?
    B: Slightly lower, but the deviation can still be controlled within ≤3mm/m, meeting requirements.

  32. A: 抛丸后的钢材表面有手印污染,影响底漆附着力。
    B: 要求操作人员戴手套接触,污染部位重新处理。
    A: The shot-blasted steel surface has fingerprint contamination, affecting primer adhesion.
    B: Require operators to wear gloves, and reprocess contaminated areas.

  33. A: 分段的焊接变形采用机械矫正,效果比火工矫正好吗?
    B: 对于薄板效果更好,可避免热变形影响。
    A: Mechanical straightening is used for section welding deformation. Is it better than flame straightening?
    B: Better for thin plates, avoiding thermal deformation effects.

  34. A: 磁粉探伤的磁痕显示模糊,是对比度不够吗?
    B: 是的,更换高对比度磁粉,确保磁痕清晰。
    A: The magnetic particle indication is blurred. Is it due to insufficient contrast?
    B: Yes, replace with high-contrast magnetic particles to ensure clear indications.

  35. A: 板材剪切后的平面度超差,是剪床间隙调整不当导致的吗?
    B: 是的,重新调整剪床间隙至板厚的 10-15%。
    A: The flatness of the sheared plate is out of tolerance. Is it caused by improper adjustment of the shearing machine gap?
    B: Yes, readjust the gap to 10-15% of the plate thickness.

  36. A: 总段的水平度采用水准仪测量,精度能满足要求吗?
    B: 能满足,水准仪精度为 ±1mm,符合测量要求。
    A: The block's levelness is measured with a level. Can the accuracy meet the requirements?
    B: Yes, the level accuracy is ±1mm, meeting measurement requirements.

  37. A: 焊接工艺卡中的预热温度与实际不符,需要修改吗?
    B: 需要,按实际检测的环境温度调整预热温度。
    A: The preheating temperature in the welding process card is inconsistent with the actual. Does it need modification?
    B: Yes, adjust the preheating temperature according to the actual ambient temperature.

  38. A: 数学放样的坐标数据与 CAD 模型不符,哪里出错了?
    B: 是数据转换时的单位错误,已统一为毫米单位。
    A: The coordinate data of mathematical lofting does not match the CAD model. What went wrong?
    B: It's a unit error during data conversion. Unified to millimeters.

  39. A: 酸洗后的中和处理不彻底,钢材表面 pH 值呈酸性。
    B: 延长中和时间,确保 pH 值达到 7-8。
    A: The neutralization after pickling is incomplete, and the steel surface pH is acidic.
    B: Extend neutralization time to ensure pH reaches 7-8.

  40. A: 肋骨安装的垂直度用线锤测量,偏差有 2mm/m。
    B: 符合要求,允许偏差≤3mm/m。
    A: The perpendicularity of frame installation is measured with a plumb bob, with a deviation of 2mm/m.
    B: It meets the requirements; the allowable deviation is ≤3mm/m.

  41. A: 激光切割的板材出现热变形,是切割速度太慢导致的吗?
    B: 是的,提高切割速度 5%,减少热输入。
    A: The laser-cut plate has thermal deformation. Is it caused by too slow cutting speed?
    B: Yes, increase the cutting speed by 5% to reduce heat input.

  42. A: 密性试验的合格标准是什么?有轻微渗漏允许吗?
    B: 不允许,必须无任何渗漏,压力保持稳定。
    A: What's the qualification standard for tightness test? Is slight leakage allowed?
    B: No, there must be no leakage, and the pressure must remain stable.

  43. A: 分段的临时加强材焊接在受力区域,影响结构强度。
    B: 移至非受力区域焊接,减少对母材的影响。
    A: The temporary stiffeners of the section are welded in the stressed area, affecting structural strength.
    B: Move to non-stressed areas for welding to reduce impact on the base material.

  44. A: 焊缝的余高打磨后出现凹陷,是打磨过度导致的吗?
    B: 是的,控制打磨量,确保不低于母材表面。
    A: The weld reinforcement has depressions after grinding. Is it caused by excessive grinding?
    B: Yes, control the grinding amount to ensure it's not lower than the base material surface.

  45. A: 抛丸机的除尘效果差,工作环境粉尘浓度超标。
    B: 清理除尘器滤芯,确保粉尘浓度≤10mg/m³。
    A: The dust removal effect of the shot blasting machine is poor, and the dust concentration in the working environment exceeds the standard.
    B: Clean the dust collector filter to ensure dust concentration ≤10mg/m³.

  46. A: 板材拼接的焊缝余高一边高一边低,不均匀。
    B: 调整焊接速度和电流,确保余高均匀。
    A: The weld reinforcement of the plate butt joint is uneven, with one side higher than the other.
    B: Adjust welding speed and current to ensure uniform reinforcement.

  47. A: 渗透探伤的清洗不彻底,有残留渗透剂导致假显示。
    B: 增加清洗时间,确保无残留后再涂显像剂。
    A: The penetrant testing cleaning is incomplete, with residual penetrant causing false indications.
    B: Increase cleaning time to ensure no residue before applying developer.

  48. A: 肋骨冷弯后的圆弧半径用样板检查,偏差有 10mm。
    B: 重新调整弯圆机参数,使偏差≤5mm。
    A: The arc radius of the cold-bent frame is checked with a template, with a deviation of 10mm.
    B: Readjust the bending machine parameters to make deviation ≤5mm.

  • 发表于 2025-08-15 12:22
  • 阅读 ( 34 )

你可能感兴趣的文章

相关问题

0 条评论

请先 登录 后评论
海贼王
海贼王

海员-二管轮

210 篇文章

作家榜 »

  1. 海员学院 344 文章
  2. 织光 247 文章
  3. 青衫故人 237 文章
  4. 四处漂泊 225 文章
  5. 海员 223 文章
  6. 海贼王 210 文章
  7. 朱亚文 192 文章
  8. 笑的太拽 185 文章

文件生成中...

请稍候,系统正在生成您请求的文件

请点击下载或复制按钮进行操作